Planning a Biological Atlas:
Reflections on the Ontario Experience
Paul Eagles and David Balser
Ontario Atlas Project
Recently, a number of people have been discussing the possibility of starting a new
collection of field data for an atlas of the plants or the herpetofauna of the Province of
Ontario. These ideas flow naturally out of the success of the Ontario Breeding Bird Atlas.
Much has been learned about the operation of an atlas project from the Bird Atlas
project, which might be of assistance to others who are considering the planning and
operation of a biological atlas project. It is essential that preplanning of an atlas be
as thorough as possible. There were two years of methodological preparation put into the
Bird Atlas (1979 and 1980), but this was insufficient in several ways which we will
discuss below.
The major items to be considered are: scale, field methodology, institutional
structure, administration, staffing, funding, data handling, and analysis.
Scale
Decisions must be made early on the scale of the project: all of the province or only a
portion thereof? We are quite thankful now that some people pushed hard for all of Ontario
to be included in the Bird Atlas, but the size of the project dictated that different
sizes of data collection unit would have to be used in different parts of the province.
For example, in southern Ontario, comprehensive coverage was the goal, using the 10 X 10
km UTM grid, while in northern Ontario data were collected from individual 10 km squares
within 100 X 100 km blocks. This system is quite feasible for a large area such as Ontario
(over 1 million sq. km.), but it does add complexity to the system and requires the use of
the two-map format used in the Atlas: one for southern Ontario by 10 km square, and one
for all Ontario by 100 km block.
The necessity of keeping the data collection unit consistent across the entire province
was not recognized in the initial stages of the project, and as a result we have some data
for 100 km blocks without any idea of what 10 km square it was collected in. This problem
was largely solved part way through the project.
In Ontario and in Canada as a whole, it is probable that all future atlases will
utilize the 10 X 10 UTM grid system for data collection. The UTM grid is printed on all
Canadian topographic maps and is being used for atlas projects in Ontario, Quebec, the
Maritimes, and Alberta. This helps ensure that data from provincial atlases can be
combined into a national atlas data base as it becomes available. It would also be of
tremendous research potential to be able to undertake correlations between the data for
different life forms, and with physiographic data.
In remote areas individual 10 X 10 squares could be "sampled" within some
larger unit of measurement. In the case of rare species the specific 6 digit number UTM
code could be used to locate the exact location of specific records.
At the same time it is reasonable to consider the coverage of the entire province in
any future atlas. It has been proven that it can be done and the resultant data base is
more valuable than if it was only a portion of the province. The resolution of the data in
northern Ontario is obviously very coarse, but this must be measured against the vastness
of the area and the paucity of data which existed previously.
Field Methodology
It is essential that the details of field methodology be worked out well in advance of
any field data collection. The important factors that need to be considered here are:
- all species in a group or a subset thereof -degree of evidence necessary - use of
standardized definitions (where such exist) - timing of data collection
- amount of field time required
- minimum level of expertise of field researcher
- training of field researcher
We assume that all future atlas projects will use largely volunteer labor backed up by
certain levels of technical expertise of a more professional nature.
Institutional Structure
The institutional structure of the organization for the operation of the project is of
critical importance. Our experience has confirmed our belief that all major groups
involved in a particular field must be involved in the planning and operation of a project
from the very start. This would include all government agencies, museums, university and
college departments, NGOs and major corporations that would have interest in the field.
There are many diverse aspects of running a project which require effective management:
Who will run the operation? Who raises the money, hires the staff, encourages the
volunteers, pays the bills, owns the data, receives requests, answers questions, prints
and distributes materials?
The Ontario experience suggests that a non-governmental organization was an excellent
choice as administrative home for an atlas project. The Federation of Ontario Naturalists,
with the assistance of the Long Point Bird Observatory, played a key role in the Bird
Atlas project and would be ideal candidates for any future projects. Governments and
universities, as institutional homes for atlas projects, suffer from a number of drawbacks
which volunteer groups do not. Usually, the moat important advantage of a volunteer group
is that of independence. Such a group can act quickly over a wide area and with
flexibility. Such factors are often limited in large government or quasi-government
agencies. A number of bird atlases in other countries are faltering because they are being
operated on too narrow an institutional base with the concurrent lack of potential,
profile, and administrative capability.
Administration
The Bird Atlas was basically governed by two committees - the management committee and
the technical committee. The former dealt with such items as intergroup cooperation,
project structure, funding, staffing, budgeting and project development. The latter dealt
with methodological issues such as data handling, interpretation of field data, field card
and instruction booklet design, field work design and error checking. These committees
served two vital purposes: project Supervision, and communication back to the institutions
represented by each committee member. The committees were very carefully designed so that
representatives from a large number of agencies and groups were present.
A worthwhile variation on this type of structure (that of having each project sponsored
and administered on an ad hoc basis) is that which has developed in Great Britain, where
the national government has established an agency, the Biological Records Centre, to serve
as the central repository for all of their various atlas projects. Their staff serve as
advisors on all major aspects of new and ongoing projects. We have no similar group in
Canada so if an atlas is to run its fullest potential it must raise money to hire a staff.
Staffing
Any atlas project without a permanent staff person will simply not work at all
effectively. There is only so much that volunteers can be asked to do and the drudgery of
project administration is not one of them. The responsibilities of the hired staff would
includes
- overall coordination
- training of volunteers
- data handling
- communication between and among volunteers
- fund raising
- communication among agencies
- mobilization of resources
- hiring subordinates
- production of written materials (newsletters, pamphlets, interim reports)
- methodology development
Our experience with the Ontario atlas was that a minimum of two, and as many as six,
full time staff members were required at various stages in the project, with the greatest
effort being required in data review and in the production of the book.
Funding
Very little can be done without some funding. The Ontario Breeding Bird Atlas made a
decision that a certain level of base funding was necessary for such items as two staff,
printing, data handling, office expenses, travel, telephone, mailing and computer time.
This base budget amounted to approximately $60,000 per year. Other monies were raised for
specific projects such as data collection in remote areas, computer software development
and computer equipment. In total, $70,000 of funds and equipment were utilized in the 8
years of the Ontario Breeding Bird Atlas.
If sufficient funding is not available for a basic level of administration, it would be
better to hold off on a field project until a later date. This might be preferable to the
operation of a sputtering effort which operates intermittently according to the
availability of funds or the interest of a volunteer coordinator.
The Bird Atlas was able to raise such excellent levels of support because it was well
thought through at a professional level. A hastily conceived project would not have been
able to obtain the approval of those in government and industry who are well versed in
project administration, especially in these days of fierce competition for funds.
Data Handling
The handling of the data for the Bird Atlas was not at all well thought through when
the project started in 1981. But since that time, very hard work by a number of people,
including a full-time programmer for the last four years, has resulted in a sophisticated
computer-based data handling system. All the data is stored on the IBM mainframe computers
at the University of Waterloo. Two microcomputers and three output devices (two printers
and a plotter) are dedicated exclusively for atlas use. In addition, large printers and
plotters are available at the University when necessary. The computer system is used for:
- editing the data (in flat files using a full-screen editor) - error checking by means of
various programs
- integration of new data into existing files
- analysis of data
- output of data in a wide variety of formats, including maps, charts, lists, reports and
summaries
- storage on tape and disk
- word processing and typesetting
- specialized data analysis
With over 400,000 records there is no other way of handling the information. Any new
atlas must consider its data handling needs well before any field collection should take
place. For example, the design of the field card can influence to a large degree the
efficiency of data input, and determine the information which can be extracted later. The
data card used by the Ontario atlas did not, for instance, allow for the recording of the
exact date of each sighting, and hence it is often impossible to say just when a suspected
migrant wee seen.
Another primary consideration is the hardware and software required. The Ontario atlas
used SAS as the software package for handling the data base, BASIC for driving a desktop
plotter, and custom software for driving the laser scanner-plotter used to produce the
publication-quality maps in the Atlas. Since the Ontario project got underway in the early
1980s, more sophisticated relational data base management systems have become available,
including some good packages for microcomputers. The value of SAS on the other hand, is
that it allows for program development for almost any conceivable purpose, is widely used
and well supported, and is available in compatible mainframe and microcomputer versions.
Certainly any project beginning now would want to consider using the very powerful
microcomputers which are now available. For some applications, it would be worthwhile to
have such a microcomputer connected to a mainframe computer. This would allow access to
the powerful data processing capabilities of the larger machine. It would also allow
access to the many output devices that are usually attached to mainframes in a large
computer establishment. As a relevant example, this paper wee composed on a Digital
microcomputer in Paul Eagles' office, then edited on a similar machine that wee located in
Dave Balser's office and connected to the Eagles' machine via a computer network. The
finished product then was transferred to a VAX mainframe computer, then to an IBM
mainframe computer, both at The University of Waterloo, in Waterloo, Ontario. The paper
wee then electronically transferred via an inter-university computer network to Charlie
Smith 'a computer account at the Cornell Laboratory of Ornithology at Ithaca, New York.
One final cautionary note concerns software development. It might be assumed that moat
of the programming required would be to develop or implement a mapping system. This is a
major task, of course, but at least as much effort wee devoted to producing summaries,
lists, and specialized reports for regional coordinators, authors, editors and those
scrutinizing the data.
Analysis
One important aspect of any database is its use. The Bird Atlas database is now in
active use by a variety of people, and it is hoped that the number of researchers using
the data will increase as demonstrations of its utility and potential are provided. For a
database to be utilized efficiently there needs to be a basic administrative structure in
place. The following items need to be addressed:
- Who has access to the data?
- In what forma are the data available?
- Can unique searches of the data baas be done for the individualized needs of users?
- Is there a person available to answer the telephone, accept mail inquiries and advise on
the availability of the data?
- Is there a charge for the information? - How fast can the data be accessed?
In summary, we have learned a lot from our efforts in regards to the Bird Atlas. This
information could be of use to others who are considering the establishment of new atlas
projects. We would like to encourage such initiatives and are willing to provide
assistance.